A Project Manager is in the process of evaluating and prioritizing risks on the project by calculating the Risk Priority Number (RPN) for the risks. A Risk priority number will consider which factors?
A.Probability, Impact, and Timeframe
B.Probability, Impact, and owner
C.Probability, Impact, and Cost
D.Probability, Impact, and Schedule
Answer is A.
Why not C ? please explain