Q: You are halfway through a major network rollout project. A software seller has just released major software upgrade for some of the equipment being installed . The upgrade will provide the customer the functionality which they requested that wasn't available when the project began . What is the best course of action:
A: Continue as planned , customer has not requested a change
B:Inform customer of upgrade and impact on project timeline and functionality if upgrade is implemented...
Gold Plating question - need clarification
A: Continue as planned , customer has not requested a change
B:Inform customer of upgrade and impact on project timeline and functionality if upgrade is implemented...
Gold Plating question - need clarification