Hi Experts,
Wanted to understand the sequence of activities that happen during change management:
1) A change is required and it comes in from customer/internal sources
2) A root cause analysis is done to identify the source of change
(If you can fix the problem at the root, fix it without the need for change management process, else proceed to step 3)
3) A change request is raised with the root cause details
4) The PM and his team perform impact analysis, where they look at the impact of the...
Change Management Sequence
Wanted to understand the sequence of activities that happen during change management:
1) A change is required and it comes in from customer/internal sources
2) A root cause analysis is done to identify the source of change
(If you can fix the problem at the root, fix it without the need for change management process, else proceed to step 3)
3) A change request is raised with the root cause details
4) The PM and his team perform impact analysis, where they look at the impact of the...
Change Management Sequence