Quality Management Question

$
0
0
The testing results for a new computer modulation project indicate a problem with on board computer sensors and project manager calls a meeting with team to analyze the problem . The project manager is involved in :

A.Quality Management Plan
B.Perform Quality Assurance
C.Plan Quality
D.Perform Quality control

Since the PM is conducting meeting and performed the testing I gave option B as this is the only one in Execution process group however answer given is D . Please help explain