I have doubt in the below question. I think the low risk situation is Fixed price incentive as seller will not only do the work in required fixed price, but it will get an incentive if the performance is good.So the answer should be b.
But the answer mentioned is a.
View attachment 432 Type
I have doubt in the below question. I think the low risk situation is Fixed price incentive as seller will not only do the work in required fixed price, but it will get an incentive if the performance is good.So the answer should be b.
But the answer mentioned is a.