You are executing a project when the customer asks for a change that's going to increase the schedule risk. What should you do first?
1) Inform your manager about customer request
2) Inform the customer that the project would get delayed
3) Analyze the impact of the change with your team
4) Go ahead and accept the change
1) Inform your manager about customer request
2) Inform the customer that the project would get delayed
3) Analyze the impact of the change with your team
4) Go ahead and accept the change