Can you explain why this is a LAG and not a LEAD.
The way I read this is that the activity for design which is month long started and after 15 days of Design the Review started:
design is 30 days
DESIGN
REVIEW (starts 15 days after design so review has a lead of 15 days).
Please explain if I have misunderstood the question.
154. You are a Project Manager, managing a large software project. It has a month long design phase in which the team would be preparing the design documents for...
PMP exam 2 question