You are a Project Manager, managing a large software project. It has a month long design phase in which the team would be preparing the design documents for independent project modules. The activity review for these modules can begin 15 days after starting the design phase. The 15 days difference between the start of the design phase and the start of the review activity show - - - - -between the...
Leads and Lags
You are a Project Manager, managing a large software project. It has a month long design phase in which the team would be preparing the design documents for independent project modules. The activity review for these modules can begin 15 days after starting the design phase. The 15 days difference between the start of the design phase and the start of the review activity show - - - - -between the...