What are constructive changes w.r.t the question below? The correct answer is option B. However, is there a simpler explanation to explain a constructive change?

Constructive changes are a common source for conflicts between customers and contractors in projects under contract. What is a constructive change?
A change request that helps improving the project and its product, service, or result and could be generally discussed in a friendly style.
A direction by the buyer or an action taken by...

Oliver lehman questions-Query 6

Tricky questions. Spl Attn. All Trainer!

$
0
0
Hi, I am posting this thread to post practice questions where I am finding it difficult to answer, and asking everyone to help with the explanation. If anybody has questions they can also post here.
Requesting all the trainers to help the learners here.
Thank you!

Query

$
0
0
Why is the PM not included in the count? The correct answer is D. As per the solution, the total number of stakeholders is 10+2-1.

You are in charge of a project that deals with laying out a lavish 18-hole golf course. The project work is in progress. You also have a number of contractors working on the project. Being an experienced manager you know that communication is key to success of the project. You have identified 10 stakeholders with whom you need to...


Query

Oliver lehman questions-Query 7

Big Data Hadoop and Spark Developer| Rakesh | March 23rd - April 28th

$
0
0
Hi Learners,

Kindly post your queries below.

Happy Learning,

Regards,
Neha Pandey

Query

$
0
0
How do we know which EAC formula to use in which scenario?

You are assigned as the project manager to a project which had a one-time cost variance in the past caused by unexpected rework which has meanwhile been finished. You expect future costs of the project as was originally planned

You perform earned value analysis and get the following results:
EV: 250,000; PV: 200,000; AC 275,000

BAC is 500,000.

What is right?
EAC = 550,000
EAC = 525,000
EAC = 500,000
EAC = 425,000

Anoop|April 13

Query

$
0
0
What is the meaning of Jerry B. Harvey's concept called the "Journey to Abilene"?

Project managers should visit their customers far more often than what is usual in order to avoid misunderstandings and bad emotions.
International projects may have an increased need for traveling which can lead to additional costs and troubles with time zones.
Group decisions can have the paradox outcome, that a decision is jointly made or approved that is not desired by any of the group members.
A project is a...

Query

SRIDHAR PMP BATCH 20TH APRIL19

SRIDHAR BATCH 9TH MARCH'19

SRIDHAR PMP FEB23RD BATCH

Query

$
0
0
The correct answer is A. What is a dangle?
You have just created the following network logic diagram to describe the planned flow of activities for your project which will start tomorrow:

[​IMG]

Which potential inconsistency in the diagram should you solve right now to ensure that the activities and the milestones "Start" and "A-F finished" are correctly linked?
Activity E is open ended (a "dangle") in...

Query

Query for AOA critical analysis

$
0
0
Can you please guide me on this question?

A Project Manager is using AOA to perform critical path analysis. The network diagram is represented as shown using below. Which of the following represents the path:

Activity Duration Dependent on
A 3 none
C 3 none
B 2 Dependent on -A
D 5 Dependent on -C
E 2 none
F 4 Dependent on -E
G 3 Dependent on -D,F
H 1 Dependent on -D,F
I 2 Dependent on -B,G
R 0 Dependent on - H,I

Query

$
0
0
A prime contractor in a customer project under CPFF contract has run into unexpected technical problems through no fault of their own. Fixing these problems will require a lot of additional work to be done.

The company made a decision to book more staff and equipment from their subcontractors in order to increase productivity and adhere to the agreed timeline. The overhead work for the project is reimbursed by the customer with the fixed fee and will remain unchanged. The customer agreed to...

Query

Query

$
0
0
A production process has been defined as part of an industrial equipment manufacturing project. The process is intended to produce steel bolts with a length of 20 cm. The control limits are 19.955cm and 20.045cm.
The measurements made at the end of the process yielded the following results:

20.033cm, 19.982cm, 19,995cm, 20.056cm, 19.970cm, 19.968cm, 19.963cm, 19.958cm, 19.962cm, 19.979cm, 19.929cm.

What should be done?

Options:
The process is under control. It should not be adjusted.
The...

Query

April 5th Batch| Mr Kumar

Query

$
0
0
A manager who manages a collection of projects grouped together to facilitate effective management to meet strategic business objectives is called a:
SELECT THE CORRECT ANSWER

Program Manager
Portfolio Manager
Project Manager
Stakeholder
Correct Option:B

Isn't (A) Program manager the correct answer?

Query

$
0
0
You found the following earned value analysis information for a project that was recently closed-out:

SPI = 0.7, CPI = 1.0

The project has been cancelled while it was executed. At that time the project was behind schedule and on budget.
The project's deliverables have all been finished. The project came in behind schedule but on budget.
The project's deliverables have all been finished. The project came in ahead of schedule but on budget.
The project's deliverables have all been finished. The...

Query

Query

$
0
0
The correct answer is the first choice, but is there such a formula EAC=BAC-CV?

You are performing earned value technique on your project.
After budget approval, an additional and unexpected cost item has been identified, which made the project more expensive some weeks ago. The item has meanwhile been paid by the project, and it is expected that for the remaining duration of the project, costs will be as budgeted.

In this case, which is the best formula to calculate EaC (Estimate at...

Query

Query

$
0
0
A project was planned to take 5 months. The team is currently 3 months into it and has completed half of the work.

Applying Earned schedule technique, what are the performance data of the project?

SV: -0.5 months, SPI: 0.83
SV: 1.5 months, SPI: 1.5
SV: -2,5 months, SPI: 0.83
SV: 0.5 months, SPI: 1.83